Road Projects

This page displays projects of all impact levels and in all regions by default. To view projects only in certain regions or impact levels, please select the region to the right, and/or the impact level below.

To search for a specific project or event, use the search function at the top right.
Show Only Region: 
Highest Impact Medium Impact Neighborhood and Local Impact Night & Overnight Impact View All What are these?

Columbus Road Resurfacing

Resurfacing work by Columbus and other jurisdictions continues to be very active across Central Ohio. Please give crews room to work and watch carefully for flagging operations, equipment  and  crews at work on resurfacing jobs. Some helpful general information about the resurfacing processes and a list of City of Columbus Streets scheduled for resurfacing this year is available at: https://www.columbus.gov/resurfacing/

(Columbus)

2017 Glove Box Guide Construction Overview

Paving the Way’s Glove Box Guide, an overview of Central Ohio’s road-construction projects planned for 2017, is now available on the Paving the Way website. The Guide includes a map of planned projects and information on work-zone safety, sharing the ride and other resources to help Central Ohio motorists, cyclists and pedestrians get to their destinations safely.

View or download the guide at: http://bit.ly/ptwgbg17

South Side 'Mega Fix' Between Grove City and Columbus

The South Side 'Mega Fix' is a five-mile ODOT construction project on Interstate 71 between Columbus and Grove City that will build extra lanes, new bridges and exit ramps. The $113 million project will be under construction for three years with completion planned for the Fall of 2020. 

Various overnight lane restrictions will be in place. The entrance ramp from Greenlawn Avenue to I-71 northbound will close temporarily for 15 days sometime in July 2018. 

More information on the project can be found here.

(ODOT)

Cannon Drive Relocation / State Route 315 Closures

State Route 315 Ramp Closures

Starting June 11 and continuing through late November 2018, the entrance ramp to southbound SR-315 at Cannon Drive and 12th Avenue will be closed, as well as Cannon Drive between 12th Avenue and Herrick Drive (which will remain closed until 2019).

Motorists may use Neil Ave. to exit this area of campus. Detour signs will be posted. Dates are weather dependent and subject to change. 

The northbound SR- 315 exit ramp to Medical Center Drive / King Avenue will remain closed through mid-August 2018. Motorists may use Goodale St. to Neil Ave., or Lane Ave. to Olentangy River Rd. 

---

View construction detours and Cannon Drive Relocation Project websites for additional information. The project will straighten and elevate Cannon Drive to provide future flood protection and open up 12 acres of developable land. The first phase of construction is expected to last through the fall of 2019.

(Ohio State)

South Old State Road Improvements

Crews have begun work this week on the South Old State Road Project. The roadway will be reconstructed and widened between Polaris Parkway and Orange Road. Watch for equipment and crews at work in this area. At least one lane of traffic will be maintained in each direction. Some closures of side streets are expected.

Motorists should plan for brief delays on South Old State Road and may wish to consider US 23 or Worthington Road via Polaris Parkway as alternate routes. The project includes new sidewalks and a shared-use path and is scheduled to be completed in the fall of 2018. For more information on this and other Delaware County projects, visit www.co.delaware.oh.us/engineer  (Delaware County/Columbus) 

Parsons Avenue Street Rehabilitation Project

Parsons Avenue will be reduced to southbound-only traffic between E. Broad Street and Franklin Avenue, beginning Monday, April 24, for a street rehabilitation project, weather permitting. The project includes pavement reconstruction; installation of curb bumpouts; sidewalk widening; signal upgrades and other improvements. The project is scheduled to be complete by Spring 2018.

The detour for northbound traffic is E. Town Street, west to S. Washington Avenue, north to E. Broad Street and east, back to Parsons Avenue.

For more details see the Project Fact Sheet at http://bit.ly/parsonsbroad

(Columbus Public Service)

High Street Streetscape Improvements

In mid-April, the primary streetscaping activities as part of phase II will begin . This includes new sidewalks, planters, street lighting and traffic signals from W. Poplar Ave. to W. Starr Ave. 

Various intermittent restrictions and closures are taking place. Construction acitivies are schedule to continue through November 2018.

Project highlights:

  • Building sidewalks, Americans with Disabilities Act-compliant curb ramps and curb extensions
  • Resurfacing the roadway
  • Adding brick crosswalks
  • Improving storm sewers and water lines
  • Planting street trees and landscaping
  • Installing iron tree grates and refuse containers
  • Upgrading street lighting, traffic signals, crosswalk signals and signage
  • Adding shared lane markings for bicycle traffic within the street

Access to area businesses will be maintained. For more details and regular updates, please see: https://www.columbus.gov/highstreet/  

(Columbus)

Parsons Avenue Improvements E. Livingston Avenue to Hosack Street Start Monday

Crews will start work on Monday, May 22, on the Parsons Avenue Improvements: E. Livingston Avenue to Hosack Street. Watch for crews and equipment at work. One lane of traffic will be maintained in each direction during construction.  Improvements include resurfacing, signal upgrades, ADA-compliant ramps, on street bicycle accommodations and bump-outs. The work is expected to continue through summer 2018, weather permitting For more information see: https://www.columbus.gov/publicservice/streets/project-information/Parsons-Avenue-Improvements-Livingston-to-Hosack/ (Columbus Public Service)

West 3rd Avenue Widening near Railroad between Edgehill Road and Columbus Fire Station #25

Eastbound 3rd Avenue is detoured at Northwest Boulevard, except for local business traffic. This detour is expected to be in place for the rest of the year.

This is for a widening, reconstruction and pedestrian path project -- part of which includes the railroad bridge.

The project will facilitate traffic flow, improve safety and provide pedestrian and bicyclist accommodations with the following improvements:

  • Widening and reconstructing the roadway
  • Constructing a new two-span railroad bridge
  • Building curbs, Americans with Disabilities Act-compliant curb ramps (ADA), sidewalks and a shared-use path
  • Upgrading street lights, signs and underground cables for traffic signals
  • Planting street trees and landscaping
  • Installation of  new traffic signals at:
    • Edgehill Road and W. 3rd Avenue
    • Edgehill Road and W. 5th Avenue

All bridge work is expected to finish in February 2019. Road and sidewalk work will start once the bridgework is complete.

Please drive with extra caution through this and all road-construction work-zones. More information on this project is available at: http://www.columbus.gov/publicservice/streets/project-information/3rd-Avenue-between-Edgehill-Road-and-fire-station/

(City of Columbus)

SR 310 Widening

SR 310 (Hazelton-Etna Rd SW) in Licking County will be widened and improved between US 40 (National Road SW) and I-70 beginning Monday, June 12. Two-way traffic will be maintained. Expect occasional flagging operations between  9 a.m. and 3 p.m. and between 7 p.m. to 6 a.m.  Estimated Completion: Fall 2018, weather permitting. (ODOT)

On the Map: https://goo.gl/maps/dyZMTvtY8by

Ramp from Main Street to Interstate 71 South

The ramp from Main Street to Interstate 71 south is closed to complete work on I-70 (part of the Crossroad corridor). 

The detour is: Rich St. to 3rd St. to I-71 south.

(ODOT)

I-70 West Into Downtown Between 18th and Grant Reduced to One Lane

East Side drivers headed downtown via Interstate 70 will notice a new traffic pattern just before the I-70/71 split.

I-70 west is reduced to one lane between 18th Street and Grant Avenue to construct a retaining wall along the interstate. That means I-70 west thru traffic and traffic headed to I-71 south have to merge into the left lane sooner than they did prior to construction.

Drivers are encouraged to follow the signs and choose their lane early. 

This $41 million project is the first of five projects to improve the I-70/71 corridor. The first project will build a new wider bridge at Grant Avenue as well as make improvements to Mound and Fulton. Completion is expected to be in the fall of 2018.

East Dublin-Granville Road Closure Between Old Hamilton and Hamilton

Dublin-Granville Road between Old Hamilton Road and the Hamilton Road S Curve will be closed beginning Monday (8/14) for several months as part of the new Dublin-Granville Road Realignment project.

This will be a full closure and the road will reopen in early spring of 2018, after the new road has been completed.

Detours are being set up down Old Hamilton Road through the S Curve.

(City of Columbus)

Cleveland Avenue and Schrock Road Improvements

Cleveland Avenue between I-270 and Schrock Road will have intermittent lane closures for an expansion project. 

The project will make the following improvements:

  • Additional northbound and southbound lanes along Cleveland Avenue
  • Additional eastbound lanes on Schrock Road to provide dual left and dual right turn lanes onto Cleveland Avenue
  • Installing new sidewalk on the north side of Schrock Road between Schrock Hill Court and Cleveland Avenue
  • Extending the multi-use path on th east side of Cleveland Avenue from I-270 north to JP Morgan Chase & Co. signal with connections to Sharon Woods Metro Park and Mt. Carmel St. Ann's
  • Improving streen lighting and utilities

Completion: December 2018

For more information: http://westerville.maps.arcgis.com/apps/Shortlist/index.html?appid=37b3f438706b4f989d515d82ac0d18c4

(City of Westerville)

High Street Beween Hull Street and East Hubbard Ave

Beginning Nov. 6, work will get under way at 800 North High Street – a new private development project being built on the east side of High Street. This means the far east lane of High Street will be closed and all east-side meters between Hull Street and East Hubbard Avenue will be bagged. The four meters on East Hubbard Avenue will be bagged and the sidewalk on the south side of this road will be closed to pedestrians to accommodate needs of the work zone and maintain safety. In addition, approximately the first 200 feet of North Pearl Street from East Hubbard Avenue southward will be closed for work zone activities.

Expect pedestrian access through this area and to businesses to be fully maintained on both sides of High Street. It will also be maintained on the north side of East Hubbard Avenue for continued access to these businesses as well as the Hubbard Garage. These restrictions will be in place for approximately 19 months throughout the build-out, with completion slated for May 2019.

Grant Avenue Bridge Closing

At 8 a.m. on January 9, the Grant Avenue Bridge, which crosses I-70/71 will close in preparation to be demolished and replaced. This is part of the current construction project to improve the Interstate 70/71 downtown 'split'. The new Grant Avenue bridge is expected to open later this fall.

The detour is: 

Southbound Grant Ave. Detour: Mound St. WB to 3rd SB to Livingston head east.

Northbound Grant Ave Detour: Livingston EB to Parsons NB to Main St. head west.

 

Along with a new bridge at Grant Avenue, the current project improves Mound Street between 4th and High Streets by adding granite curbs, brick crosswalks, decorative signals, lighting and landscaping. The project also converts Fulton Street to one-way eastbound from 4th to Washington.

The $31 million project which started this past spring is expected to be complete by late fall 2018.

(ODOT)

Mound Street Reconstruction

Monday March 5, Mound Street becomes one way for WB only traffic between Fourth and Front.

Reconstruction of Mound Street begins March 5 and will continue until fall 2018,  weather permitting.

(ODOT)

Highway Ramp Closures South of Downtown Tonight 3/13

Please note that a series of highway ramps south of downtown will close between 9 p.m. and 5 a.m. tonight.

I-71 at I-70

  • 9:00 PM Monday March 12 - Thursday March 15: The ramp from 70 EB to 71 SB will be closed for lighting removal. Detour 70 EB to 71 SB: 315 NB to US-33 WB to 315 SB to 71 SB.
  • 5:00 AM Thursday March 15: Each morning the ramp will open.

I-71 at Greenlawn Ave.

  • 9:00 PM Monday March 12 - Thursday March 15: The ramp from 71 SB to Greenlawn Ave. will be closed for lighting removal. Detour 71 SB to Greenlawn Ave.: Continue SB to SR-104 to 71 NB to Greenlawn Ave.
  • 5:00 AM Thursday March 15: Each morning the ramp will open.

I-71 between SR-104 and I-70

  • 7:00 PM Monday March 12 - Tuesday March 13: 71 NB will be reduced to two lanes for pavement repairs.
  • 9:00 PM: 71 NB will be reduced to one lane.
  • 5:00 AM: All lanes open.

I-71 at I-270

  • 9:00 PM Monday March 12 - Friday March 16: The ramp from 71 SB to 270 EB will be closed for bridge demolition. Detour: 71 SB to Stringtown Rd to 71 NB to 270 EB.
  • 5:00 AM Each morning all lanes open

Hyland-Croy Road/Post Road Signal Improvements

Work on signal improvements at the intersection of Hyland-Croy Road and Post Road in Dublin began April 9, 2018.

There will be an intermitten right lane closure on eastbound Post Road between Post Preserve Boulevard and US 33.

Completion is scheduled for July 2018.

(City of Dublin)

East Gay Street and Cleveland Avenue - Creative Campus Streetscape Project

East Gay Street from Cleveland Avenue to North Washington Avenue is closed, and Cleveland Avenue is one-lane northbound only from Broad Street to Long Street.

The closures are part of the Creative Campus streetscape project, which will reconstruct Gay Street. Improvements include brick/pavers for the pavement, raised intersection tables at Cleveland Avenue, 9th Street and North Washington Avenue. Also included are new sidewalks with streetscape elements that will help enhance East Gay Street as a more pedestrian-friendly environment.

Construction is scheduled to be completed September 2018, with landscaping running through November.

(City of Columbus)

Waggoner Road north of Broad Street

The northbound curb lane of Waggoner Road will be closed north of Broad Street, including one left turn lane eastbound on Broad Street. 

Overmont Ridge Road and Dolmen Drive will also experience closures.

These closures are part of a widening and construction of a shared use path on Waggoner Road from Broad Street to Chapel Stone Road.

The project is expected to be completed in October 2018.

Warner Road Closure between Hamilton and Harlem

Warner Road between Hamilton Road and Harlem Road will be closed for 60 days starting on April 16. 

The first two weeks will close the bridge over Rocky Fork.  The remaining four weeks will close 600 feat of roadway at the Harlem end for street reconstruction. 

Local access will be maintained, but detoured around the closures.

(City of Columbus)

Livingston Avenue Bridge Over Blacklick Creek Lane Closures

Lane closures will begin April 16 and be reopened in mid-September for a bridge deck replacement on Livingston Avenue over Blacklick Creek. 

Livingston Avenue will be reduced from four lanes to two lanes, with two-way traffic.

The project is expected to be completed in late October.

(Franklin County Engineer)

South Hamilton Road and East Livingston Avenue Lane Closures

Starting April 16, the following lane closures will take place for improvements:

Livingston Ave:

  • The curb lane on westbound Livingston, starting at Hamilton and heading west, will be closed for 900 feet. The remaining westbound lane will remain open.

Hamilton Road:

  • The curb lane on southbound Hamilton, starting at Livingston and heading south, will be closed for 900 feet. The remaining southbound lane will remain open.

The closures will be in place for 45 days.

(City of Columbus)

Dublin Road Closure Between Trabue and Roberts

Starting Monday, May 14, Dublin Road will close between Trabue Road and Roberts Road for a sewer line project. The work will begin at the Trabue Road intersection and work its way north. Local access will be maintained coming from the north (Roberts Road), and eventually switching to come from the south.

The project is expected to be completed in five weeks (approximately June 18), weather permitting.

(City of Columbus)

Glick Road Tunnel Repair

Beginning May 7 crews will remove and replace two timber retaining walls adjacent to the tunnels under Glick Road between Avery Road and Muirfield Drive.

Traffic Impact  

  • Interment lane closures of Glick Road
  • One lane two-way traffic will be maintained with flaggers between 7:30am to 5:00pm

 

The project is expected to be completed September 2018.

(City of Dublin)

High Street and East Dominion Lane Restrictions

Beginning June 4, High Street will experience lane restrictions and changes in traffic patterm at the intersection of East Domion for ADA ramp and crosswalk work.

Temporary signals will be place when the traffic pattern shifts. 

These traffic impacts should be expected over a four-week period (approximately July 4th).

(City of Columbus)

US 33 Widening on Southest Side

The Ohio Department of Transportation (ODOT) project to widen US 33 in both directions between I-270 and SR 317/Hamilton Road started Monday, May 14, 2018.  Once complete, there will be three travel lanes for both east and westbound travel on US 33. The project will also widen the bridges over Big Walnut Creek. Work will occur in the existing right-of-way and does not require additional land. All lanes on US 33 will be resurfaced. 

The purpose of this project is to improve travel and safety on US 33 between these two interchanges and decrease congestion. Just over 73,000 vehicles use US 33 between Hamilton Road and I-270 each day. More information is on ODOT's website.

Traffic will be maintained during construction using temporary pavement. Nighttime and weekend lane and ramp closures are permitted with posted detours. To receive notifications of traffic impacts, go to transportation.ohio.gov and enter your email address. 

The $14 million project is expected to be complete Fall of 2019.

(ODOT)

Godown Road between Linworth Road and Smallwood Drive

The southbound lane on Godown Road is closed from Linworth Road to Smallwood Drive. This is part of the Silver Drive Area Water Line Improvements project.

The northbound lane will remain open but will be shifted with barrels. The road will opened back up in 90 days (approximately the beginning of September).

(City of Columbus)

Alum Creek Drive Closure Between Refugee Road and Frebis Avenue

Norfolk Southern will be closing Alum Creek Drive at the railroad crossing between Refugee Road and Winslow Drive from June 11-15.

There will be access for local traffic from both the north and the south up to the track, but no crossing. 

Maize Road Between Morse and Cooke

The northbound lane on Maize Road will be closed from Morse Rd to Cooke Rd. This will be for the Maize Road Area Water Line Improvements Project.

The southbound lane will remain open but will be shifted around with barrels.

The closure will be opened back up in 90 days (approximately September), weather permitting.

(City of Columbus)

Route 605 Between New Albany Road and Walnut Street

The southbound lane of Route 605 – also known as New Albany-Condit Road – will be closed between New Albany Road and Walnut Street. The northbound lane will remain open.

The closure will be for a road-widening project by the New Albany Co. It is for Nottingham Trace, a Pulte Homes development that will include 240 age-restricted homes off Schleppi Road, and will accommodate the future home of Canine Companions for Independence at 7444 New Albany-Condit Road, he said.

The closure will last for up to 75 days (mid to late August).

 

Arcadia Avenue Area Water Line Improvements

The Arcadia Avenue Area Water Line Improvements project will begin the week of June 11. Arcadia Avenue will be closed to westbound traffic until mid-August 2018 between High Street and Indianola Avenue, and detour signs will be posted.

The project also includes work on the following streets: Arcadia, Northwood, Patterson, Maynard, East, Blake, Duncan, Calumet, Adams, Medary, Mood, Northridge, Blemhien, Dorko, Weibel and Oakland Park (from I-71 to Cleveland). Please be aware of various lane restrictions and closures throughout the project, which is scheduled to last approximately 15 months (August/September 2019).

(City of Columbus)

Columbus Pride Festival & Parade Street Closures

The Columbus Pride Festival & Parade will take place this weekend, Friday and Saturday. The festival begins Friday afternoon at 4 p.m. and will include street closures along Genoa and Bicentennial parks. These include Washington Boulevard, Rich Street, Civic Center Drive, and Main Street.

The parade will form at Goodale park at 8 a.m. Saturday morning and officially step off at 10:30 a.m. The parade route will begin from Goodale park, heading south on High until turning west on Broad Street and ending at Washington Boulevard/Genoa Park.

Please consider walking, biking, taking transit or carpooling.

Darby Creek Drive Closed South of West Broad Street

Darby Creek Drive will be closed south of West Broad Street (US 40/National Road) from June 18-22 for drainage repairs   

The posted detour route for southbound motorists on Darby Creek Drive will follow West Broad Street (US 40/National Road) east to Murnan Road, south to Alton Road, south to Alkire Road and west to Darby Creek Drive.  Northbound traffic will follow the detour route in the opposite direction.

Approximate closure date: June 18 to June 22, 2018 weather permitting.

(Franklin County Engineer)

Nelson Road Between Franklin Park South and Broad

Beginning June 18, the northbound lane of Nelson Road Between Franklin Park South and Broad Street will be closed for a resurfacing project.

The project is expected to be completed in 6-8 weeks (early August).

(City of Columbus)

Scioto Darby Road and Leppert Road Reconstruction

Work is taking place for the reconstruction of Scioto Darby Road and Leppert Road.

The project will provide substantial improvements to Scioto Darby Road, which will include constructing two roundabouts, new curbs and multi-use paths, as well as lighting and landscaping, this summer and next. 

The project is taking place in phases and includes a closure of Leppert Road at Scioto Darby to the north at the Heritage Trail crossing until the end of August 2018.  

The completion date of the project is October 2019, weather permitting.

(City of Hilliard)

Columbus Department of Public Service Road Project Fact Sheets

Columbus Department of Public Service Road Project Fact Sheets (current and future project overviews)

Columbus Street Sweeping

Columbus Street Sweeping

City of Columbus street sweeping schedule updates are available at:  https://www.columbus.gov/publicservice/streets/Street-Sweeping/

(Columbus)

 

View Archived Projects